Next Steps

Thank you for taking the time to view our consultation website on early ideas for the area around High Barnet station.

Project Timeline:

November and December 2024

First round of public consultation on early plans

February / March 2025

Second round of public consultation on updated plans

Spring 2025

Submission of planning application to London Borough of Barnet

Autumn 2025

Determination of planning application by London Borough of Barnet

Early 2026

Work starts on site

2029

Construction works complete / first homes delivered

We want to hear from you

Your feedback matters to us and has helped to shape the proposals for High Barnet.

Thank you to everyone who attended one of our consultation events both this year and last. We were delighted to welcome more than 800 people to our public exhibitions and community webinars and to hear your views and feedback on the scheme.

We are currently reviewing the feedback received, however you can still submit an online feedback form here.

Once we have analysed all feedback and finalised our proposals, we will submit a planning application to the London Borough of Barnet later this year.

Get in touch

If you have any questions, or would like the information displayed in an alternative format, please get in touch with the project team using the details below: